Which of the following is the statutory body that regulates and registers engineers in Nepal, as distinct from the voluntary professional society?
सही उत्तर: ख) Nepal Engineering Council
The Nepal Engineering Council is the regulatory body created by statute; the Nepal Engineers' Association is a professional membership organisation.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Under the Nepal Engineering Council Act, 2055, a person who wishes to practise the engineering profession in Nepal must first:
सही उत्तर: ख) Have his or her name registered with the Nepal Engineering Council
The Act makes registration with the Nepal Engineering Council mandatory for practising engineering in Nepal.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In Nepal, which part of the Nepal National Building Code deals with the seismic design of buildings?
सही उत्तर: घ) NBC 105
NBC 105 is the code for seismic design of buildings in Nepal.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In building estimates, wall plastering is usually measured and paid in units of:
सही उत्तर: क) Square metres
Plastering, painting and similar surface finishes are measured by area (m²), while masonry and concrete are measured by volume (m³).
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
At 10% annual compound interest, what is the present worth of Rs 1,21,000 to be received after 2 years?
सही उत्तर: घ) Rs 1,00,000
PW = F/(1 + i)ⁿ = 1,21,000 / (1.10)² = 1,21,000 / 1.21 = Rs 1,00,000.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The total float of an activity in CPM is calculated as:
सही उत्तर: ग) Latest start time minus earliest start time
Total float = LST − EST (equivalently LFT − EFT), the time an activity can be delayed without delaying project completion.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In network analysis, the critical path is the path that:
सही उत्तर: क) Has the longest total duration and activities with zero total float
The critical path is the longest path through the network; delay in any of its activities delays the whole project.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In PERT, an activity has optimistic time 4 days, most likely time 6 days and pessimistic time 14 days. What is its expected time?
सही उत्तर: ख) 7 days
te = (to + 4tm + tp)/6 = (4 + 24 + 14)/6 = 7 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Which statement correctly distinguishes CPM from PERT?
सही उत्तर: ग) CPM uses deterministic activity times while PERT uses probabilistic time estimates
CPM is activity-oriented with a single deterministic duration, whereas PERT is event-oriented and uses optimistic, most likely and pessimistic estimates.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The treatment of sewage in a septic tank takes place mainly through:
सही उत्तर: घ) Anaerobic decomposition
In a septic tank, settled solids are digested by anaerobic bacteria in the absence of oxygen.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।