A brick wall is 5 m long, 3 m high and 0.23 m thick. Taking 500 bricks per m³ of brickwork, the number of bricks required is about:
सही उत्तर: ख) 1725
Volume = 5 × 3 × 0.23 = 3.45 m³; bricks = 3.45 × 500 = 1725.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking dry volume as 1.54 m³, the volume of sand required for 1 m³ of 1 : 1.5 : 3 concrete is:
सही उत्तर: घ) 0.42 m³
Sand = 1.54 × 1.5/5.5 = 0.42 m³ (coarse aggregate = 0.84 m³).
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking dry volume as 1.54 m³ per m³ of concrete and one bag as 0.035 m³, the number of cement bags for 1 m³ of 1 : 1.5 : 3 concrete is about:
सही उत्तर: क) 8.0 bags
Cement = 1.54/(1 + 1.5 + 3) = 0.28 m³; bags = 0.28/0.035 = 8.0.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A nominal concrete mix of 1 : 3 : 6 is commonly used for:
सही उत्तर: ख) Plain cement concrete in foundation beds (M10)
1:3:6 (about M10) is a lean mix used for levelling courses and foundation beds, not for structural RCC.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The nominal mix proportion (cement : sand : aggregate) traditionally corresponding to M20 concrete is:
सही उत्तर: ग) 1 : 1.5 : 3
Traditional nominal mixes: M10 = 1:3:6, M15 = 1:2:4, M20 = 1:1.5:3, M25 = 1:1:2.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking the bulk density of cement as 1440 kg/m³, the number of 50 kg bags in 1 m³ of cement is:
सही उत्तर: घ) 28.8
Bags = 1440/50 = 28.8 bags per cubic metre.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An estimate prepared every year to keep a building in proper condition (white washing, minor repairs, etc.) is the:
सही उत्तर: घ) Annual repair (maintenance) estimate
Annual repair/maintenance estimates provide for periodic work such as white washing, painting and minor repairs.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Technical sanction of a public work is normally given on the basis of the:
सही उत्तर: ग) Detailed estimate with drawings and specifications
Technical sanction is the competent engineer's approval of the detailed estimate, design and drawings; administrative approval is generally based on the preliminary estimate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The cube rate estimate of a building is obtained by multiplying the cube rate by the:
सही उत्तर: घ) Plinth area × height of the building
Cube rate estimate = cubical contents (plinth area × height) × cube rate; it is more accurate than the plinth area method for buildings of varying height.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An approximate estimate of a hospital obtained by multiplying the number of beds by the cost per bed is based on the:
सही उत्तर: क) Service unit method
The service (unit) method uses cost per functional unit, e.g. per bed for hospitals or per student for schools.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।