An estimate prepared for additional work found necessary while the original sanctioned work is in progress is called a:
सही उत्तर: घ) Supplementary estimate
A supplementary estimate covers extra work over and above the original estimate; it shows the original and additional amounts.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A revised estimate is prepared when:
सही उत्तर: ख) The original sanctioned estimate is likely to be exceeded significantly or the work is materially changed
A revised estimate replaces the sanctioned estimate when costs rise beyond the permissible limit or design changes materially; extra new items go in a supplementary estimate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Pointing on brick or stone masonry is measured in:
सही उत्तर: ग) Square metre
Pointing is a surface treatment of joints and is measured by area of the face in m².
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In estimating, wooden door and window frames (chaukhat) are usually measured in:
सही उत्तर: घ) Cubic metre
Timber in frames is measured by volume (m³), while door and window shutters are measured by area (m²).
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Water supply and sanitary pipelines are measured in an estimate in:
सही उत्तर: क) Running metre
Pipes of a stated diameter are measured by length along the centre line, in running metres.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In a building estimate, damp proof course (DPC) is measured in:
सही उत्तर: ख) Square metre (m²)
DPC of specified thickness is measured by area in m²; its thickness is stated in the item description.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In irrigation planning, a canal must irrigate 4000 ha of a crop whose duty at the head of the canal is 1000 ha/cumec. The required canal capacity is:
सही उत्तर: घ) 4 m³/s
Discharge = area/duty = 4000/1000 = 4 m³/s.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An escape in a canal system is provided to:
सही उत्तर: क) Dispose of excess water from the canal safely into a natural drain
Canal escapes discharge surplus water (e.g. during sudden closure or heavy rain) to protect banks from breaching.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A stilling basin below a spillway is designed mainly to:
सही उत्तर: क) Contain the hydraulic jump and dissipate energy before water re-enters the river
Stilling basins (e.g. USBR types) force a hydraulic jump within a protected apron so the high-velocity flow does not scour the river bed.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The Chandra Canal (Chandra Nahar) in Saptari district is commonly cited as:
सही उत्तर: घ) The first modern government-built irrigation canal of Nepal
Chandra Nahar, built during the Rana period (around 1922), is regarded as Nepal's first modern irrigation canal constructed by the government.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।