A radial gate commonly used on spillways and barrages is also known as a:
सही उत्तर: ख) Tainter gate
A radial (Tainter) gate has a curved skin plate and rotates about a horizontal trunnion; its water thrust passes through the pin, so it is easy to operate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The most common cause of failure of earth dams is:
सही उत्तर: घ) Overtopping by floods
Inadequate spillway capacity leading to overtopping causes rapid erosion of an earth dam; piping and slope failure are other major causes.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A shaft (morning glory) spillway is one in which water:
सही उत्तर: ख) Enters a funnel-shaped crest and drops through a vertical shaft into a tunnel
In a morning glory spillway the circular crest feeds a vertical shaft connected to a horizontal conduit; side channel spillways flow parallel to the crest.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A fish ladder at a weir or barrage is provided to:
सही उत्तर: क) Allow migratory fish to pass upstream across the structure
A fish ladder (fish pass) is a series of pools or baffles that lets fish move past the structure.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A divide wall at diversion headworks is provided to:
सही उत्तर: ख) Separate the undersluice pocket from the main weir and create a still pond near the head regulator
The divide wall forms a still pocket in front of the head regulator so silt settles and can be sluiced out, and keeps cross-currents away.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A barrage differs from a weir mainly in that:
सही उत्तर: ख) The pond level is controlled mainly by gates, with a low or no raised crest
In a barrage most of the ponding is done by gates over a low crest; in a weir the raised crest does most of the ponding.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A weir floor has 30 m of horizontal creep and two vertical cut-offs giving 8 m of total vertical creep, under a head of 4 m. Lane's weighted creep ratio is:
सही उत्तर: ख) 4.5
Weighted creep = 8 + 30/3 = 18 m; ratio = 18/4 = 4.5.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
According to Lane's weighted creep theory, horizontal creep lengths are counted at what fraction of vertical creep lengths?
सही उत्तर: घ) One-third
Lane found vertical paths more effective in resisting seepage, so weighted creep = vertical length + (1/3) horizontal length.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
At a diversion headworks, a silt excluder is constructed:
सही उत्तर: क) In the river bed in front of the head regulator to prevent bed silt from entering the canal
A silt excluder (undersluice pocket) keeps silt out at the head; a silt ejector (extractor) removes silt that has already entered the canal.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A canal fall is provided where:
सही उत्तर: घ) The natural ground slope is steeper than the designed canal bed slope
Falls drop the canal bed in steps so that the bed slope remains as designed while following a steeper terrain.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।