सिभिल इन्जिनियरिङ
सिभिल इन्जिनियरिङ
Civil Engineering · ५,१७१ प्रश्न
५,१७१ प्रश्न उपलब्ध। मोड छान्नुहोस्:
सिभिल इन्जिनियरिङ: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ३ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
High strength deformed steel bars for concrete reinforcement are specified in:
सही उत्तर: ग) IS 1786
IS 1786 covers high strength deformed bars (Fe 415, Fe 500, etc.); IS 2062 covers structural steel and IS 800 steel design.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The Indian Standard that gives guidelines for concrete mix proportioning (mix design) is:
सही उत्तर: ग) IS 10262
IS 10262 gives the procedure for concrete mix proportioning; IS 456 is the code for plain and reinforced concrete.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Steel and concrete work well together in RCC partly because they have:
सही उत्तर: ख) Nearly equal coefficients of thermal expansion
Their thermal expansion coefficients are similar (about 10–12 × 10⁻⁶ /°C), so temperature changes do not break the bond.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Ferrocement consists of:
सही उत्तर: घ) Thin sections of rich cement mortar reinforced with closely spaced layers of fine wire mesh
Ferrocement uses cement-sand mortar with multiple layers of small-diameter wire mesh, giving thin, strong, crack-resistant elements such as water tanks.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Heavyweight concrete made with aggregates such as barytes or magnetite is used mainly for:
सही उत्तर: ख) Radiation shielding, for example in nuclear plants and X-ray rooms
High-density aggregates give concrete of high unit weight that absorbs gamma and X radiation effectively.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A small amount of sugar accidentally mixed into fresh concrete will:
सही उत्तर: घ) Retard the setting of cement
Sugar is a powerful retarder; even small doses delay setting and large doses can prevent hardening altogether.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
As per IS 456, formwork to vertical faces of walls, columns and beams may generally be struck after:
सही उत्तर: क) 16 to 24 hours
Vertical formwork carries no load once concrete has set, so it can be removed after 16–24 hours with OPC under normal conditions.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
As per IS 456, with ordinary Portland cement and normal temperature, the formwork props to slabs spanning up to 4.5 m may be removed after:
सही उत्तर: ग) 7 days
IS 456 recommends props to slabs up to 4.5 m span after 7 days (14 days over 4.5 m); props to beams up to 6 m after 14 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The Kelly ball test measures the workability of fresh concrete by:
सही उत्तर: ग) The depth of penetration of a hemispherical ball of standard weight
In the Kelly ball test, a 13.6 kg hemispherical ball is placed on the concrete surface and its penetration is measured.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The flow table test of fresh concrete is mainly suitable for:
सही उत्तर: ग) Highly workable (flowing) concrete
The flow test measures the spread of concrete on a jolted table and is used for concrete of high workability.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।