In the long wall-short wall method, if the centre-to-centre length of a long wall is 6 m and wall thickness is 0.3 m, the out-to-out length of the long wall is:
सही उत्तर: ग) 6.3 m
Long wall out-to-out = c/c length + one wall thickness = 6 + 0.3 = 6.3 m.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A rectangular building has external dimensions 10 m x 8 m with all walls 0.3 m thick. The total centre line length of the walls is:
सही उत्तर: ख) 34.8 m
2 x [(10 - 0.3) + (8 - 0.3)] = 34.8 m.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In earthwork, the term 'lead' means:
सही उत्तर: ग) Horizontal distance over which excavated earth is carried
Lead is the horizontal haul distance; lift is the vertical distance.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A trench 10 m long, 0.8 m wide and 1.0 m deep is excavated. The quantity of earthwork is:
सही उत्तर: क) 8.0 m3
10 x 0.8 x 1.0 = 8.0 m3.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An embankment has a formation width of 10 m, height 2 m and side slopes 2H:1V. Its cross-sectional area is:
सही उत्तर: क) 28 m2
A = (b + s d) d = (10 + 2 x 2) x 2 = 28 m2.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Two cross-sections of an embankment 50 m apart have areas 20 m2 and 30 m2. By the average end area (trapezoidal) method the volume is:
सही उत्तर: क) 1250 m3
V = 50 x (20 + 30)/2 = 1250 m3.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The prismoidal formula for earthwork volume is applicable when the number of cross-sections is:
सही उत्तर: क) Odd
The prismoidal (Simpson's) rule needs an even number of intervals, that is, an odd number of sections.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A Bill of Quantities (BOQ) issued with tender documents mainly contains:
सही उत्तर: क) Description of items with their quantities, to be priced by bidders
The BOQ lists work items and quantities for the bidders to quote rates.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The document that gives the total cost of all items by multiplying their quantities with unit rates is called:
सही उत्तर: घ) Abstract of estimate
The abstract of estimate sums quantity times rate for every item.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Rate analysis of an item of work means:
सही उत्तर: ग) Determining the cost per unit of the item including materials, labour, equipment, overheads and profit
Rate analysis works out the unit rate from its cost components.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।