The document that gives the total cost of all items by multiplying their quantities with unit rates is called:
सही उत्तर: घ) Abstract of estimate
The abstract of estimate sums quantity times rate for every item.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Rate analysis of an item of work means:
सही उत्तर: ग) Determining the cost per unit of the item including materials, labour, equipment, overheads and profit
Rate analysis works out the unit rate from its cost components.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Contingencies in an estimate are generally provided at about:
सही उत्तर: घ) 3 to 5 percent of the estimated cost
A small allowance of about 3 to 5 percent covers unforeseen minor items.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A building has a plinth area of 120 m2 and the plinth area rate is Rs 25,000 per m2. Its approximate cost is:
सही उत्तर: ख) Rs 30,00,000
120 x 25,000 = Rs 30,00,000.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The plinth area of a building is calculated by taking:
सही उत्तर: क) External dimensions of the building at floor level, excluding plinth offsets
Plinth area is the covered built-up area measured from the outer faces of walls at floor level.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Which of the following is NOT a type of approximate estimate?
सही उत्तर: ख) Detailed estimate
A detailed estimate is prepared from item-wise quantities and rates, not by approximate methods.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The volume of one 50 kg bag of cement taken in estimating is about:
सही उत्तर: घ) 0.035 cubic metre
With bulk density 1440 kg/m3, 50/1440 is about 0.0347 cubic metre.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
To obtain the dry volume of materials for 1 cubic metre of wet (finished) cement concrete, the wet volume is commonly multiplied by about:
सही उत्तर: क) 1.54
Dry materials shrink in volume after mixing with water, so about 1.52 to 1.57 (commonly 1.54) times the wet volume is taken.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Using the modular brick size with mortar of 20 cm x 10 cm x 10 cm, the number of bricks in 1 cubic metre of brickwork is:
सही उत्तर: ग) 500
1 / (0.2 x 0.1 x 0.1) = 500 bricks per cubic metre.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Formwork (shuttering) for RCC members is usually measured in:
सही उत्तर: ख) Square metre of contact area
Formwork is measured as the area of the form in contact with concrete.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।