In PERT, an activity has optimistic time 3 days and pessimistic time 15 days. Its variance is:
सही उत्तर: घ) 4 days^2
Variance = [(15 - 3)/6]^2 = 4.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In PERT, an activity has optimistic time 4 days and pessimistic time 16 days. Its standard deviation is:
सही उत्तर: ग) 2 days
Standard deviation = (16 - 4)/6 = 2 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Which statement about CPM and PERT is correct?
सही उत्तर: घ) CPM is deterministic and activity-oriented, while PERT is probabilistic and event-oriented
PERT uses three time estimates to handle uncertainty, while CPM uses a single fixed duration.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Public procurement in Nepal is mainly governed by the:
सही उत्तर: घ) Public Procurement Act, 2063
The Public Procurement Act, 2063 (2007) regulates public procurement in Nepal.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The register used to record daily attendance and wages of labourers employed on departmental work is the:
सही उत्तर: ख) Muster roll
The muster roll records attendance and wages of daily labour.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The Measurement Book (MB) is used to:
सही उत्तर: ख) Record measurements of work done, which form the basis of payment
All payments to contractors are based on measurements recorded in the MB.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A contract in which the contractor is paid the actual cost of work plus an agreed fee is called:
सही उत्तर: ग) Cost-plus contract
In a cost-plus contract payment equals actual cost plus a fixed or percentage fee.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Retention money deducted from the contractor's bills is mainly kept to:
सही उत्तर: ग) Cover defects that appear during the defect liability period
A portion of each bill is retained and released after defects are remedied.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Performance security is furnished by the contractor to:
सही उत्तर: ख) Guarantee proper execution of the contract
Performance security protects the employer against failure to perform the contract.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Earnest money (bid security) is taken from bidders mainly to:
सही उत्तर: क) Ensure that a bidder does not withdraw or back out of the bid
Bid security is forfeited if the bidder withdraws or refuses the contract.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।