इन्जिनियरिङ सेवा सिभिल इन्जिनियर (सातौँ तह) – प्राविधिक पत्र
इन्जिनियरिङ सेवा – सिभिल इन्जिनियर (सातौँ तह)
Civil Engineer – 7th Level · Engineering Service
१,५०३ प्रश्न उपलब्ध। मोड छान्नुहोस्:
प्राविधिक पत्र: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ५ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
For a cantilever of length L carrying a point load W at its free end, the maximum bending moment occurs at the fixed end and equals:
सही उत्तर: ख) WL
Moment at the fixed support = load x lever arm = WL.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A simply supported beam of 6 m span carries a UDL of 20 kN/m over the whole span. The maximum bending moment is:
सही उत्तर: ग) 90 kN·m
M = wL²/8 = 20 x 6² / 8 = 90 kN·m.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The maximum bending moment in a simply supported beam of span L carrying a uniformly distributed load w per unit length is:
सही उत्तर: ग) wL²/8
For a simply supported beam with UDL, maximum moment at mid-span is wL²/8.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In compass surveying, local attraction at a station is detected when:
सही उत्तर: ख) Fore and back bearings of a line differ by other than 180°
In the absence of local attraction, fore and back bearings differ by exactly 180°.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The whole circle bearing of a line is 210°. Its reduced (quadrantal) bearing is:
सही उत्तर: क) S 30° W
For WCB between 180° and 270°, RB = S (WCB - 180°) W = S 30° W.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A back sight of 1.250 m is taken on a benchmark of RL 100.000 m, and a fore sight of 2.100 m is taken on point P. The RL of P is:
सही उत्तर: क) 99.150 m
HI = 100.000 + 1.250 = 101.250 m; RL of P = 101.250 - 2.100 = 99.150 m.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Closely spaced contour lines on a map indicate:
सही उत्तर: क) A steep slope
Small horizontal spacing for the same contour interval means the ground rises steeply.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The fundamental principle of surveying is to work:
सही उत्तर: ग) From whole to part
Working from whole to part localises errors and prevents their accumulation.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
For a concrete mix with water-cement ratio 0.45, the quantity of water required for one 50 kg bag of cement is:
सही उत्तर: ग) 22.5 litres
Water = 0.45 x 50 kg = 22.5 kg, i.e. 22.5 litres.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The soundness of cement is tested using:
सही उत्तर: ख) Le Chatelier apparatus
Le Chatelier apparatus measures expansion of cement, which indicates its soundness.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।