प्राविधिक पत्र: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ५ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
By the constant percentage (declining balance) method at 10% per year, a machine costing Rs 1,00,000 will have a book value after 2 years of:
सही उत्तर: क) Rs 81,000
1,00,000 x 0.9 x 0.9 = Rs 81,000.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
By the straight line method, an asset costing Rs 5,00,000 depreciates at Rs 30,000 per year. Its book value after 5 years is:
सही उत्तर: क) Rs 3,50,000
5,00,000 - 5 x 30,000 = Rs 3,50,000.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Straight line method: a building costs Rs 5,00,000, has scrap value Rs 50,000 and life 15 years. Annual depreciation is:
सही उत्तर: ख) Rs 30,000
(5,00,000 - 50,000)/15 = Rs 30,000 per year.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A provisional sum in a contract is:
सही उत्तर: घ) An amount included for work that cannot be fully defined at the time of tendering
A provisional sum covers work whose details are not known when the tender is prepared.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
As per the common measurement rule (IS 1200), in brickwork no deduction is made for openings each up to:
सही उत्तर: ख) 0.1 m2
Small openings up to 0.1 m2 each are not deducted from brickwork quantity.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Using the relation W = d^2/162 (W in kg/m, d in mm), the weight of a 12 mm diameter bar 10 m long is about:
सही उत्तर: घ) 8.89 kg
144/162 x 10 = 8.89 kg.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
For 1 m3 of 1:6 cement mortar, taking dry volume factor 1.27, the volume of cement required is about:
सही उत्तर: घ) 0.18 m3
Cement = 1.27/7 = 0.18 m3.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking dry volume as 1.54 m3 and one bag of cement as 0.035 m3, the number of cement bags required for 1 m3 of 1:2:4 concrete is about:
सही उत्तर: घ) 6.3 bags
Cement = 1.54/7 = 0.22 m3, and 0.22/0.035 = about 6.3 bags.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The centre line method of estimating is most suitable when:
सही उत्तर: ग) Walls are of similar cross-section throughout the building
The centre line method gives accurate results when wall sections are uniform.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In the long wall-short wall method, if the centre-to-centre length of a long wall is 6 m and wall thickness is 0.3 m, the out-to-out length of the long wall is:
सही उत्तर: ग) 6.3 m
Long wall out-to-out = c/c length + one wall thickness = 6 + 0.3 = 6.3 m.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।