In levelling, a larger staff reading on a point compared with another, from the same instrument set-up, means that the point is:
सही उत्तर: ग) Lower
The line of sight is horizontal at one height, so the further down it meets the staff (larger reading), the lower the ground point is.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Ranging rods used for marking survey stations are usually of length:
सही उत्तर: घ) 2 m or 3 m
Ranging rods are commonly 2 m or 3 m long, circular in section, with a pointed iron shoe at the lower end.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A 'swing offset' in chain surveying is taken by:
सही उत्तर: ख) Swinging the tape about the object point and finding the shortest distance to the chain line
The perpendicular from a point is the shortest distance, found by swinging the tape until the reading on the chain line is minimum.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A chain is tested before use by:
सही उत्तर: घ) Comparing it with a standard length (test gauge) marked on the ground
Chains are checked against a test gauge established with a standard steel tape and adjusted if too long or too short.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
For laying sewers to a given gradient, sight rails are fixed at the ends of a section and the invert levels are checked with a:
सही उत्तर: क) Boning rod (traveller)
A boning rod of fixed length sighted between sight rails shows whether the trench bottom or pipe invert is at the required gradient.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In hydrographic surveying, a graduated pole used for measuring shallow depths is a:
सही उत्तर: क) Sounding rod
Sounding rods are used for shallow water; for greater depths a lead line or echo sounder is used.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In adjusting survey observations, the weight assigned to an observation is:
सही उत्तर: क) Inversely proportional to the square of its standard error (variance)
More precise observations get higher weight: weight ∝ 1/σ².
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The probable error of a single observation is related to its standard deviation σ by:
सही उत्तर: ख) Probable error = 0.6745 σ
Half of the errors are expected to be smaller than the probable error, which equals 0.6745 times the standard deviation.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A Triangulated Irregular Network (TIN) represents a terrain surface by:
सही उत्तर: घ) Non-overlapping triangles joining irregularly spaced points of known elevation
In a TIN, sampled points are joined into triangles (often Delaunay), with denser triangles where the terrain is complex.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A Digital Elevation Model (DEM) is:
सही उत्तर: क) A digital representation of ground surface elevations
A DEM stores terrain heights, usually in a grid, for analysis such as slope, drainage and visibility.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।