Bulking of sand is caused by:
सही उत्तर: ग) Thin films of surface moisture around the sand particles
Surface moisture films push particles apart and increase the bulk volume of damp sand.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Abrams' law states that the strength of fully compacted concrete depends mainly on its:
सही उत्तर: घ) Water–cement ratio
Abrams' law relates concrete strength inversely to the water–cement ratio.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
As per IS 456, exposed surfaces of concrete made with OPC should be kept moist for at least:
सही उत्तर: ग) 7 days
IS 456 requires a minimum of 7 days moist curing for OPC concrete.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The characteristic strength of concrete is defined as the strength below which not more than:
सही उत्तर: ख) 5% of the test results are expected to fall
IS 456 defines characteristic strength at 5% probability of lower results.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In the designation M25, the number 25 represents:
सही उत्तर: घ) Characteristic compressive strength of 150 mm cubes at 28 days in N/mm²
M stands for mix and 25 is the 28-day characteristic cube strength in N/mm².
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The nominal mix proportion for M20 grade concrete is:
सही उत्तर: ख) 1 : 1.5 : 3
M20 nominal mix is 1:1.5:3; 1:2:4 corresponds to M15.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Workability of fresh concrete is most commonly measured in the field by the:
सही उत्तर: ख) Slump test
The slump test is a simple field test for consistency and workability of concrete.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Portland Pozzolana Cement (PPC) is produced by blending OPC clinker with:
सही उत्तर: क) Pozzolanic material such as fly ash
PPC contains pozzolana such as fly ash that reacts with lime to form extra C-S-H.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The compound mainly responsible for the strength of hydrated cement paste is:
सही उत्तर: क) Calcium silicate hydrate (C-S-H) gel
C-S-H gel is the main binding phase that gives hardened cement paste its strength.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The main oxide constituent of Portland cement by percentage is:
सही उत्तर: ग) Lime (CaO)
Lime forms roughly 60–67% of Portland cement.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।