A PERT critical path consists of three activities with standard deviations 2, 3 and 6 days. The standard deviation of the project duration is:
सही उत्तर: ग) 7 days
Variances add: 4 + 9 + 36 = 49; standard deviation = √49 = 7 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In a network, A (3 days) and B (5 days) start the project, C (4 days) follows A, and D (2 days) follows both B and C. The total float of activity B is:
सही उत्तर: क) 2 days
B can start at 0 and must finish by 7 (latest start of D = 9 − 2); total float = 7 − 0 − 5 = 2 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In a network, activity A (3 days) and B (5 days) start the project; C (4 days) follows A; D (2 days) follows both B and C. The project duration is:
सही उत्तर: ख) 9 days
Path A–C–D = 3 + 4 + 2 = 9 days; path B–D = 5 + 2 = 7 days; the longest (critical) path gives 9 days.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In Nepal, electronic bidding for public procurement is carried out through the:
सही उत्तर: ख) e-GP system managed by the Public Procurement Monitoring Office
The electronic Government Procurement (e-GP) system of PPMO is used by public entities for e-bidding.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A running account (RA) bill in a works contract is:
सही उत्तर: ग) An interim bill for payment of work done up to a date, subject to adjustment in the final bill
RA bills give on-account payments based on measurements during progress; the final bill settles all amounts.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The defect liability period in a construction contract is the period:
सही उत्तर: ख) After completion during which the contractor must rectify defects at his own cost
During the defect liability period the contractor remedies defects; retention money is released after it ends satisfactorily.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Under public procurement practice, a works contract is normally awarded to the bidder who submits the:
सही उत्तर: ग) Lowest evaluated substantially responsive bid
Bids are checked for substantial responsiveness and qualification; among these, the lowest evaluated cost wins.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A pre-bid meeting during the tendering process is held to:
सही उत्तर: ग) Clarify bidders' queries about the bidding documents before bids are submitted
At the pre-bid meeting the employer answers queries; clarifications are issued to all bidders, ensuring equal information.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
'Force majeure' in a construction contract refers to:
सही उत्तर: क) Extraordinary events beyond the parties' control, such as earthquakes or war, that prevent performance
Force majeure events (natural disasters, war, etc.) excuse delay or non-performance and usually entitle the contractor to an extension of time.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A written instruction by the engineer altering the quantity, quality or nature of work under a contract is a:
सही उत्तर: क) Variation order
Variation orders change the scope of work; the changed work is valued using contract rates or newly agreed rates.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।