The right of a person to use another's land for a limited purpose, such as a right of way or passage of drainage, is called a(n):
सही उत्तर: ख) Easement
An easement is a right enjoyed over neighbouring land (e.g. light, way, drainage) without owning it.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The value of a dismantled building's materials, after deducting the cost of dismantling, is called its:
सही उत्तर: घ) Scrap value
Scrap value is the net value of materials when the structure is dismantled; salvage value is the value at the end of useful life without dismantling.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Loss in value of a property because its design or facilities have become out of date, rather than due to wear and tear, is called:
सही उत्तर: घ) Obsolescence
Obsolescence is loss of value due to outdated design, function or technology even if the structure is physically sound.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A building fetches a gross annual rent of Rs 1,20,000; outgoings are 20% of gross rent. Capitalised at 8% in perpetuity, its value is:
सही उत्तर: ग) Rs 12,00,000
Net income = 1,20,000 × 0.8 = 96,000; value = net income × YP = 96,000/0.08 = Rs 12,00,000.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A property has a life of 20 years. With 6% return on capital and a sinking fund at 4% (annual sinking fund coefficient ≈ 0.0336), the year's purchase is about:
सही उत्तर: ग) 10.69
YP = 1/(i + ic) = 1/(0.06 + 0.0336) ≈ 10.69.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The annual instalment of a sinking fund needed to accumulate Rs 1,00,000 in 10 years at 10% compound interest is about:
सही उत्तर: घ) Rs 6,275
A = S·i/[(1 + i)ⁿ − 1] = 1,00,000 × 0.1/(1.1¹⁰ − 1) = 10,000/1.5937 ≈ Rs 6,275.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The item 'work charged establishment' in an estimate provides for:
सही उत्तर: ख) Staff employed for the execution and supervision of that particular work
Work-charged staff (e.g. work supervisors, chowkidars) are employed specifically for a work and paid from the work's estimate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A 'prime cost (PC) item' in a contract is:
सही उत्तर: ग) An item of specified materials or goods to be supplied whose cost is included as a fixed sum
A PC item covers supply of specified articles (e.g. sanitary fittings) for which a fixed price is allowed; the contractor adds labour for fixing and profit.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In rate analysis, the term 'overhead' refers to:
सही उत्तर: ख) Indirect expenses such as office, supervision and establishment costs not attributable to one item
Overheads are general/indirect costs (office rent, staff, tools, insurance) spread over all items, distinct from direct material, labour and equipment costs.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In Nepal, the unit rates of materials, labour and equipment fixed annually for each district and used for preparing estimates are commonly called:
सही उत्तर: क) District rates
District rates (जिल्ला दररेट) are fixed each fiscal year at district level and used with norms to prepare cost estimates of public works.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।