लागत अनुमान र निर्माण व्यवस्थापन – Estimating & Construction Management MCQ
लागत अनुमान र निर्माण व्यवस्थापन – सिभिल इन्जिनियरिङ
Estimating & Construction Management · Civil Engineering · ४५४ प्रश्न
४५४ प्रश्न उपलब्ध। मोड छान्नुहोस्:
लागत अनुमान र निर्माण व्यवस्थापन: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ३ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
In a building estimate, damp proof course (DPC) is measured in:
सही उत्तर: ख) Square metre (m²)
DPC of specified thickness is measured by area in m²; its thickness is stated in the item description.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A project is considered economically justifiable when its benefit-cost ratio is:
सही उत्तर: क) Greater than 1
B/C greater than 1 means benefits exceed costs.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The present worth of Rs 10,000 receivable after 2 years at 10% compound interest is about:
सही उत्तर: घ) Rs 8,264
PW = 10,000/(1.1)^2 = Rs 8,264.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A firm has fixed cost Rs 2,00,000, selling price Rs 50 per unit and variable cost Rs 30 per unit. Its break-even quantity is:
सही उत्तर: घ) 10,000 units
BEP = 2,00,000/(50 - 30) = 10,000 units.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The Line of Balance (LOB) technique is especially suited to:
सही उत्तर: ग) Projects with repetitive units such as housing or road sections
LOB plans and controls the rate of output of repeated units.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Resource smoothing in project scheduling aims to:
सही उत्तर: ख) Reduce fluctuations in resource demand without changing the project duration
Smoothing uses available floats to even out resource use within the fixed duration.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A major limitation of a simple bar (Gantt) chart is that it:
सही उत्तर: ख) Does not show interdependencies between activities
Bar charts show timing but not the logical links between activities.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Fulkerson's rule in network analysis is used for:
सही उत्तर: ख) Numbering the events of a network
Fulkerson's rule gives a systematic method of numbering events.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In network analysis, the forward pass is used to find:
सही उत्तर: क) Earliest event or start times
Forward pass computes earliest times; backward pass computes latest times.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A project has expected duration 46 days and standard deviation 2 days. For a scheduled time of 50 days, the value of Z (probability factor) is:
सही उत्तर: ख) 2.0
Z = (50 - 46)/2 = 2.0.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।