लागत अनुमान र निर्माण व्यवस्थापन – Estimating & Construction Management MCQ
लागत अनुमान र निर्माण व्यवस्थापन – सिभिल इन्जिनियरिङ
Estimating & Construction Management · Civil Engineering · ४५४ प्रश्न
४५४ प्रश्न उपलब्ध। मोड छान्नुहोस्:
लागत अनुमान र निर्माण व्यवस्थापन: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ३ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
Taking the bulk density of cement as 1440 kg/m³, the number of 50 kg bags in 1 m³ of cement is:
सही उत्तर: घ) 28.8
Bags = 1440/50 = 28.8 bags per cubic metre.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An estimate prepared every year to keep a building in proper condition (white washing, minor repairs, etc.) is the:
सही उत्तर: घ) Annual repair (maintenance) estimate
Annual repair/maintenance estimates provide for periodic work such as white washing, painting and minor repairs.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Technical sanction of a public work is normally given on the basis of the:
सही उत्तर: ग) Detailed estimate with drawings and specifications
Technical sanction is the competent engineer's approval of the detailed estimate, design and drawings; administrative approval is generally based on the preliminary estimate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The cube rate estimate of a building is obtained by multiplying the cube rate by the:
सही उत्तर: घ) Plinth area × height of the building
Cube rate estimate = cubical contents (plinth area × height) × cube rate; it is more accurate than the plinth area method for buildings of varying height.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An approximate estimate of a hospital obtained by multiplying the number of beds by the cost per bed is based on the:
सही उत्तर: क) Service unit method
The service (unit) method uses cost per functional unit, e.g. per bed for hospitals or per student for schools.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An estimate prepared for additional work found necessary while the original sanctioned work is in progress is called a:
सही उत्तर: घ) Supplementary estimate
A supplementary estimate covers extra work over and above the original estimate; it shows the original and additional amounts.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A revised estimate is prepared when:
सही उत्तर: ख) The original sanctioned estimate is likely to be exceeded significantly or the work is materially changed
A revised estimate replaces the sanctioned estimate when costs rise beyond the permissible limit or design changes materially; extra new items go in a supplementary estimate.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Pointing on brick or stone masonry is measured in:
सही उत्तर: ग) Square metre
Pointing is a surface treatment of joints and is measured by area of the face in m².
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In estimating, wooden door and window frames (chaukhat) are usually measured in:
सही उत्तर: घ) Cubic metre
Timber in frames is measured by volume (m³), while door and window shutters are measured by area (m²).
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Water supply and sanitary pipelines are measured in an estimate in:
सही उत्तर: क) Running metre
Pipes of a stated diameter are measured by length along the centre line, in running metres.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।