लागत अनुमान र निर्माण व्यवस्थापन – Estimating & Construction Management MCQ
लागत अनुमान र निर्माण व्यवस्थापन – सिभिल इन्जिनियरिङ
Estimating & Construction Management · Civil Engineering · ४५४ प्रश्न
४५४ प्रश्न उपलब्ध। मोड छान्नुहोस्:
लागत अनुमान र निर्माण व्यवस्थापन: प्रश्न र उत्तर
सही लागेको विकल्पमा थिच्नुहोस्। सही भए हरियो, गलत भए रातो देखिन्छ; ३ सेकेन्डपछि सही उत्तर र व्याख्या देखिन्छ।
सही: ० / ०
-
How many 300 mm × 300 mm floor tiles (ignoring wastage and joints) are needed for a floor 4 m × 3 m?
सही उत्तर: ख) 134
Area = 12 m²; one tile = 0.09 m²; 12/0.09 = 133.3, so 134 tiles are needed.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A room 4 m × 3 m with walls 3 m high has one door 1.0 m × 2.1 m and one window 1.2 m × 1.2 m. The net internal wall plaster area (deducting both openings fully) is about:
सही उत्तर: ग) 38.46 m²
Gross = 2(4 + 3) × 3 = 42 m²; deductions = 2.10 + 1.44 = 3.54 m²; net = 38.46 m².
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
An isolated footing measures 1.5 m × 1.5 m in plan and 0.45 m in depth. The quantity of concrete is:
सही उत्तर: ख) 1.01 m³
Volume = 1.5 × 1.5 × 0.45 = 1.0125 ≈ 1.01 m³.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
In the approximate quantity method of estimating a building, the cost is worked out by:
सही उत्तर: क) Multiplying the total length of walls by a rate per running metre for foundation and superstructure
In this method the total wall length is found and multiplied by composite rates per running metre for foundation and for superstructure.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Using W = d²/162 kg/m, the weight of one 16 mm diameter bar 12 m long is about:
सही उत्तर: ख) 18.96 kg
Weight per metre = 16²/162 = 1.58 kg/m; for 12 m: 1.58 × 12 ≈ 18.96 kg.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A brick wall is 5 m long, 3 m high and 0.23 m thick. Taking 500 bricks per m³ of brickwork, the number of bricks required is about:
सही उत्तर: ख) 1725
Volume = 5 × 3 × 0.23 = 3.45 m³; bricks = 3.45 × 500 = 1725.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking dry volume as 1.54 m³, the volume of sand required for 1 m³ of 1 : 1.5 : 3 concrete is:
सही उत्तर: घ) 0.42 m³
Sand = 1.54 × 1.5/5.5 = 0.42 m³ (coarse aggregate = 0.84 m³).
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
Taking dry volume as 1.54 m³ per m³ of concrete and one bag as 0.035 m³, the number of cement bags for 1 m³ of 1 : 1.5 : 3 concrete is about:
सही उत्तर: क) 8.0 bags
Cement = 1.54/(1 + 1.5 + 3) = 0.28 m³; bags = 0.28/0.035 = 8.0.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
A nominal concrete mix of 1 : 3 : 6 is commonly used for:
सही उत्तर: ख) Plain cement concrete in foundation beds (M10)
1:3:6 (about M10) is a lean mix used for levelling courses and foundation beds, not for structural RCC.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
-
The nominal mix proportion (cement : sand : aggregate) traditionally corresponding to M20 concrete is:
सही उत्तर: ग) 1 : 1.5 : 3
Traditional nominal mixes: M10 = 1:3:6, M15 = 1:2:4, M20 = 1:1.5:3, M25 = 1:1:2.
💬 टिप्पणी / गल्ती रिपोर्ट (०)
यी अभ्यास प्रश्न हुन्, आधिकारिक प्रश्न होइनन्। पाठ्यक्रम, विज्ञापन र नतिजाका लागि सम्बन्धित निकायको आधिकारिक वेबसाइट हेर्नुहोस्। उत्तरमा गल्ती भेटे प्रश्नमुनिको "टिप्पणी / गल्ती रिपोर्ट" मा लेख्नुहोस्।
नमस्ते! पाठ्यक्रम, सामान्य ज्ञान, भाषा परीक्षा वा कुनै प्रश्नको उत्तर बुझ्न सोध्नुहोस्।
AI ले गल्ती गर्न सक्छ। महत्वपूर्ण कुरा आधिकारिक स्रोतमा जाँच्नुहोस्।